Where should wall thickness on deadlegs be monitored by the inspector?

Prepare for the API 570 Piping Inspector Test with comprehensive quizzes and detailed explanations for each question. Enhance your skills and knowledge to excel in your certification exam today!

Multiple Choice

Where should wall thickness on deadlegs be monitored by the inspector?

Explanation:
Deadlegs create zones where flow is minimal, so corrosion can develop differently than in active runs. The stagnant end is prone to deposition, chemistry changes, and corrosion under deposits, while the connection to the active line experiences different flow dynamics that can drive erosion or accelerated thinning at the weld and near the attachment. Monitoring both locations gives a complete view of wall thinning, catching problems that might only appear at one end. Therefore, the inspector should measure wall thickness at both the stagnant end and the connection to the active line.

Deadlegs create zones where flow is minimal, so corrosion can develop differently than in active runs. The stagnant end is prone to deposition, chemistry changes, and corrosion under deposits, while the connection to the active line experiences different flow dynamics that can drive erosion or accelerated thinning at the weld and near the attachment. Monitoring both locations gives a complete view of wall thinning, catching problems that might only appear at one end. Therefore, the inspector should measure wall thickness at both the stagnant end and the connection to the active line.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy